How did you manage to agree with the authorities?
It was hard to get permission?
Yes. We registered a project company at the county. We signed investment agreement with the local government, finished Feasibility Study Report, Environmental Assessment Report, Safety Production Assessment Report, etc. Many documents, many approvals, and costs.
We also purchased the land from the government, 50 years right of use. Totally about 13000 square meters.
The governor and officials visiting my farm:
https://imgur.com/w76WryK.
Is your power hydro electricity or coal based?
It's using power from the power grid, not particularly hydro or coal. So it's more stable than hydro, no need to migrate at dry seasons.
Inner Mongolia province has lots of installed capacity, including coal, wind and solar.
We construct a 10kV transmission line from the 4km far substation.
If i can ask whats ur estimated hashing power
End of year it will be 100P and next year 500P.
Photos took this morning.
https://imgur.com/LflRsKRhttps://imgur.com/tN0uOz5https://imgur.com/9hRp2PChttps://imgur.com/a7a8SCDhttps://imgur.com/e2vwX33