Delay in not being on top of the thread = been on the road show for this exact project.
{Funding Structure (for those curious) = 12 near term BTC forward contracts @ $65K ea, $750K Reg D 506 (b) Convertible Bonds seed round, $6.25M Reg D 506(c) Convertible Bonds production raise round + 20% green shoes, and 2 stand by facilities.}
So, apologies if this wasn't clear? The site isn't deployed yet (hence no pics, but I will include one of the site its self herein ;-)).
It progresses daily so I can provide rolling periodic updates here if requested.
To date...
What we have / Traction:Full C-Suite in place, and ~80% of operational personnel
Fixed price gas off-take agreement with major (publicly traded) mid stream supplier for pipeline quality gas, sufficient contract volume to power (2) ~5MW Jenbacher gen sets even presuming 100% uptime, producing kWh costs ~$.021-.033USD and gas only cost ~$12-13K per BTC (full OP-EX ~$30K per BTC).
AUC / AER / and FN (First Nations) approvals and agreements in place.
Power Generation Permit fast tracked (I'm told a week or so out now by the firm that's handling it.).
Contract for site construction, pipes, prep, rough set up, and electrical all in place.
Gen set(s) purchase and set up agreements with LOI, ongoing maintenance agreements being finalized
Bonded 3rd party site security
Applicable Insurance
----------------------------------------------------
Still sourcing -Miners, miner containers, tech stack / developer
(So some of your questions I won't have answers for but will do my best to address them in the next post).
Site is in red, fence adjacent to our midstream gas supplier which is the rest of what's in the image:
https://www.frontierpropertysolution.com/wp-content/uploads/2026/01/Screenshot-2026-01-23-191027.jpg