Feel free to ask any questions, and I will keep everyone updated as milestones are retired and the project goes along.
Was wondering where in the milestone list the pictures above are and nice setup
Project Status
Done:
June 1st - BFL announces chip sales, basic design ideas begin
June 16th - Group buy initiated
June 22nd - Group buy order placed
July 3rd - Sample chips shipped
July 12th - Samples received, final PCB review
July 14th - Test PCB sent for manufacture
July 18th - Estimated PCB ship date
Upcoming Estimates:
Week of July 22th to 28th - Begin building and testing of PCBs
Week of July 29th to August 4th - Continue testing, incorporate results into the production version
Week of August 5th to 11th - Begin taking orders for PCB sales, send out a small quantity of production boards for manufacture, finalize assembly information
Week of August 12th to 18th - Receive and build production test boards. Test, and if necessary, modify and respin board
Week of August 19th and beyond - Prepare for production, further testing and rework if needed, extra lead time. Final PCBs produced. Components ordered and stocked.
Mid September - Chips arrive and head to assembly