Do you have picture and components of part and panel ?
Please share with us
As I talked to some agent at solar saleman he told me I need at least 6000Watts of solar panel to run 1000Watts PSU for 24 hours.
My question is if I get more batteries say like 4, so I can reduce the panel watts ( from 6000 to 4000 or 3000watts )
Help please.
Really want to setup for 2 ant S3 or 1 Ant S4 (1400w)
May be invest for farm of them soon.
Pardon me for delaying the update with images and so.
I will do it soon, lazy me.
But you can ask me anything related to solar panel setup and I can guide you.
If you are taking support from agents or companies you will never ROI.
Do it yourselves by the support of forum people. I did it myself.
If you are using any good solar panels, you will get 1500W from a 2000W system during the solar time.
If you are running it 24/7 then you need a lot of battery AH and you need to charge these batteries during the day time everyday.
Batteries will never last more than 5yrs if you are discharging it to the maximum.
Else you need to buy a lot of batteries to make the discharge percentage lower.
For your need, 1400W is required 24/7 from this solar battery setup.
So around 2000W panel is required to run the miner during sun time.
Then for charging the discharged batteries daily, additional panels required.
If we calculate solar time as 6hrs (Max and too optimistic) you have 6hrs to charge the battery bank.
And your total charge backup requirement(or total charging required) is approximately, [1400*(24-6)] = 25,200 Watts (25.2KW).
That means, you need 2100AH of 12V battery. If its 6V then need 4200AH. Practically you need 3000AH atleast for 12V battery.
That's equal to 15 no of 200AH/12V Solar Battery. It will cost approximately $3500.
And to charge this much battery power during the limited 6hrs you need atleast 6000W panel. Which will cost around $4500.
Consolidating:
Panels required is more than 6000+2000 Watts Cost: $6000.
Battery 3000AH costs $3500.
Cable and other Misc: $1000 for this setup.
MPPT Charge Controllers: < $1000.
Total: $11,500 PlusNow think whether you want to setup this damp thing.
Inshort when you add more battery backup requirement you need more panels, more cables and other components.
So, if you are sure you want to go for solar just go for a Solar + Grid setup and use 400AH battery bank for emergency backup.
That will fit the budget and will ROI in 3 to 4 years if used fully. I only recommend that if you want to go for solar.
Disclaimer: All the above numbers are from rough calculations without considering losses and practical conditions.
In practical setup you may need more panels and battery so the cost will be more than what estimated here.
Again Solar is expensive as of now.